|
March 2001
Construction Engineering By Garth Greenan, P.E.
One of the keys to a well-built project is the construction engineering
services. There are four essential components to construction engineering:
construction survey, inspection, testing, and construction administration.
Not all projects require all four parts, but most projects require at
least one of these components. What is involved in each component?
Construction Survey: The locations of buildings, roads, parking
areas, and utilities are often shown on a plan, but to determine where
exactly they should build in the field requires measurements from known
points, such as property corners. Surveyors place stakes in the field
indicating to the contractor where improvements are to be located. In
addition to location, the elevations of the improvements are indicated
on the staking. Accurate placement of site improvements ensures that regulatory
requirements, such as setbacks, are met.
Inspection: Inspection includes on-site observation of the contractor's
progress. An inspector on a project does not supervise the contractor,
but works as the owner's or developer's representative at the work site.
The inspector normally keeps as-built measurements, communicates questions
and information between the contractor and engineer, and coordinates schedules
with other construction services, such as survey and testing.
Testing: Testing is done to ensure the construction methods and
materials supplied meet the specifications for the project. Some of the
common testing requirements are compaction and gradation for aggregates
and bituminous surfaces, pressure testing for piping, and compression
testing for concrete. There are a whole variety of other tests that may
be required by regulatory agencies for approvals. Coordination of the
testing is normally by the inspector working with the contractor and regulatory
agencies.
Construction Administration: There are a wide variety of issues
to track during the construction of a project. Knowing the status of the
project allows the developer or owner to determine schedules and anticipate
requests for payment from the contractor. Construction Administration
may involve only a few of the following tasks or all of them, depending
on the desires and requirements of the developer. Work tasks include preparing
bidding documents, soliciting and tabulating bids, preparation of contract
documents, reviewing contractor's insurance and bonds, preparing pay estimates,
conducting progress meetings, preparation of change orders, coordinating
with regulatory agencies for inspections, and project close-out. The complexity
of the project dictates effort required maintaining project records and
status.
Why should your engineer be involved in construction? Often it is a requirement
of the regulatory agency that the construction be inspected and certified
that it was built to the approved plans and specifications. Documentation
of the proper testing and inspections are necessary for any construction
that will become public, such as new streets, water systems or sanitary
sewers. Certifications and documentation are necessary for drainage facilities
and erosion control.
Construction Engineering provides the continuity with the designer, provides
the owner/developer with important information during construction, and
is an information conduit for the contractor.
Transaction
Information By Lee Blodgett, R.E.P.A.
The TS standard was developed for use as a formal screening method to
determine if a more in-depth investigation of a commercial property is
necessary. The TS questionnaire, the essence of the TS, asks pertinent
questions of people knowledgeable about the current and historic uses
of the property. Based on the responses received, more in-depth investigation
may either be necessary which would be focused on a particular identified
Recognized Environmental Condition (REC) or it may be necessary to expand
the assessment to a Phase I ESA.
An example of the former would be when the historic uses of the site
are known to be uses that typically would not involve hazardous substance
or petroleum product use; however, a dump site including unmarked 55 gallon
drums is observed on the property. The dump would constitute a REC and
additional investigation would be warranted. In this scenario, appropriate
inquiry may be accomplished by chemical testing of the soil and/or groundwater
underlying the dump and a Phase I may not be needed because there is acceptable
comfort otherwise in the former uses of the property.
An example of the later would be if the former uses of this property
were unknown or it is located in an area with some historic industrial
uses. The standard dictates that a presumption exists that further inquiry
is necessary in this scenario. In rebutting this presumption, the user
should evaluate information obtained from each component of the Transaction
Screen process and consider whether sufficient information has been obtained
to conclude that no further inquiry is necessary. In this scenario, reasonable
argument could be made that appropriate inquiry would require a Phase
I be conducted to thoroughly investigate former site use and whether indications
of historic activities involving hazardous substances or petroleum products
exist in historic documents or are discovered through additional interviews.
In conclusion, the decision of which level of assessment will meet the
appropriate inquiry standard for clean up liability protection is a judgement
call. This is a cost versus risk decision that an environmental consultant
should assist a user in making. However, the final decision rests with
the user.
Bulletin
EC&S is providing environmental consulting services directly for the Michigan Department of Environmental Quality to investigate potential contamination for the residue left at the site of a large tire fire near Traverse City, Michigan. EC&S has installed and sampled numerous monitoring wells and soil borings to determine the extent to which ash and buried tires have caused contamination of the underlying soil and groundwater. A hydrogeological study is being conducted to determine groundwater flow and potential contaminant transport characteristics, the extent of buried ash and tires, and an evaluation of exposure risks posed by the ash residue. Ongoing work will address source cleanup for areas of acute exposure risk. EC&S, as a result of project work on several Michigan tire fire sites, has developed a unique expertise in environmental impact and cleanup of contamination from tire fires $880,000
Brownfield Redevelopment Single Business EC&S procured one of the first Brownfield Single Business Tax Credits under PA 143. The ability to assign this SBT Credit enabled the developers of the Speareflex Project, a downtown city of Kalamazoo brownfield redevelopment, to land an anchor tenant for the project. Click here for more information. Enviromental
Bulletin
By Ben Komrska, P.G.
If your on-site assessment concludes that wetlands are present, then it is necessary to determine whether the wetland is under the State or US Army Corps' jurisdiction as this will decide if a permit from them is necessary.
Jurisdictional wetlands include:
If it is concluded that a permit is necessary, your permit application will require you to complete a wetland delineation. A wetland delineation defines the boundary of the wetlands and uplands. To perform delineation will require inspecting the properties plants, soils, and hydrology in great detail: 1. Plants--identification and location of wetland (hydrophilic) plants 2. Soils--determine if wetland characteristics are present
3. Hydrology
Once the on-site investigation and flagging is completed, a site map showing the wetland/upland boundary should be prepared for future reference. Due to the dynamic nature of
wetland resources and the ever-evolving determination methodology, wetland
determinations and delineations are valid for no more than three years,
i.e., three growing seasons. In the event that site conditions should
change prior to site development, the site investigation should be confirmed.
Land
Development News By Garth Greenan, P.E.
Brownfield Redevelopment Single Business Tax Credit A financial incentive that works By Mark Chilcott
Qualified Taxpayers can receive a Brownfield Single Business Tax Credit
equal to 10% of their eligible investment. Eligible investment activities
include demolition, building rehab/redevelopment, new construction and
equipment (for the owner of the project and/or the lessee of a project).
The Qualified Taxpayer (project owner/developer) can assign this single
business tax credit on a prorata basis to other entities that make up
the Qualified Taxpayer and/or assign the single business tax credits to
a Lessee. This is a powerful tool for attracting certain investors to
your project who can benefit from single business tax credits. Additionally,
it provides a competitive advantage to procuring tenant(s) for your project.
The brownfield project must be included in an approved Brownfield Redevelopment
Authority Brownfield Plan and a pre-approval application must be submitted
to the State. Pre-approval is necessary before eligible investment activities
can begin.
If you have a brownfield development project in process or contemplate
starting a brownfield project, utilization of the single tax credit can
improve your bottom line profitability and generate a greater return on
investment.
|
||||||||||||||||||||||||||